| 01 |
The "8-Hour Day" Illusion |
Dividing payroll by 2,080 hrs while crews spend 1.5–2.0 hrs/day on yard load-out, transit, tailgates & cleanup. |
$17,160 / mo (8-man crew) |
Divide loaded annual cost by 1,440–1,560 net billable hours. |
| 02 |
Blended Wage & OT Masking |
Bidding a blended $45/hr rate, then dispatching a $55/hr leadhand or running unbudgeted 1.5× overtime. |
$3,250 / mo (6-man crew) |
Separate leadhand, journeyperson & apprentice rates in dispatch software. |
| 03 |
"While You're Here" Scope Creep |
Executing verbal field changes without a signed Change Order; 50% go uncollected. |
~7.0% of contract value |
Require mobile digital signature + photo log before work starts. |
| 04 |
Stale Unit Rates & Buyout Slip |
Pricing tenders from 30–90-day-old supplier sheets while copper, lumber, or concrete escalates 10%+. |
$35,000+ / yr (10-person firm) |
Enforce post-award buyout audits & material escalation clauses. |
| 05 |
"Free" Paid-Off Equipment Drag |
Treating owned trucks/telehandlers (idle 28–38% of time) as free outside fuel cost. |
$21,600 / yr per $90k machine |
Bill an internal hourly/daily equipment recovery rate on every estimate. |